Public Commentary
•PDF• •Print• •E-mail•
••Thursday•, 20 •January• 2011 02:28•

THE ARTICLES BELOW ARE OPEN FOR PUBLIC COMMENT

Tshwane Rapid Transit (TRT) Line 2 Public Participation

TRT Line 2A

ArcadeStrStn A1 Poster (Rev 1)

Route 2A A1 Poster (Rev 2)

Route2A A5 Flyer (Rev 2) 2

Route2A NewspaperAd (Rev 1)

FINAL BID 7 June 2012

Presentation_21 June 2012 - IRPTN - BRT system overview

Line 2A Preliminary Design Report April 2012

ENVIRONMENTAL MANAGEMENT PLAN for the Construction of the Arcadia Street Station

Arcadia_Cons_Notice A5 Flyer (Rev 2)

1-200 5-7 GautB Provincial Gazette Line 2

BRT 2A - Feedback meeting 19 July 2012

BRT 2A heritage Assessment and Mitigation 19 July 2012

HIA FINAL SCREENING REPORT BRT LINE 2A AE01230Pa TB

Heritage Issues and responses report Heritage Aug 2012

BRT 2A - FGM 4 July 2012 Growth point minutes

BRT 2A - FGM 12 July 2012 Gautrain

TRT 2A - FGM 5 July 2012 Canadian High Commission

TRT 2A - FGM 5 July 2012 Clr Ward 92

TRT 2A - FGM 9 July 2012 Heritage Resources

275_12-9-2012_GautSeparate

HIA TSHWANE BUS RAPID TRANSIT (BRT) LINE 2A PRETORIA CENTRAL TO HATFIELD

BRT Line 2 Land Use Transportation Assessment

Tshwane Rapid Transit (TRT) Line 2 Public Participation

TRT Line 2A

Preliminary Design Drawings

CoT TRT 2A Layout Preliminary Design March 2012

Prelim Design TRT2A 1 of 19

CoT TRT Line 2A Page 2 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 3 of 19 - Preliminary Design March 2012

Prelim Design TRT2A 4 of 19

Prelim Design TRT2A 5 of 19

Prelim Design TRT2A 6 of 19

Prelim Design TRT2A 7 of 19

CoT TRT Line 2A Page 8 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 9 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 10 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 11 of 19 - Preliminary Design Page 11 of 19

CoT TRT Line 2A Page 12 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 13 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 14 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 15 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 16 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 17 of 19 March 2012

CoT TRT Line 2A Page 18 of 19 - Preliminary Design March 2012

CoT TRT Line 2A Page 19 of 19 - Preliminary Design March 2012

Park Street-Jorissen Comparison Report_08 October 2012

Systems Techncial Note 23_ParkStreet_TIA_12_10_2012 TB

Systems Technical Note 22_Line2_TIA_27_09_2012 TB

Tech Note 23 Appendix C-D_09_11_2012 TB

TECHNICAL NOTE 22_LINE 2 TIA_Appendices A_B Base Year AM Peak hour intersection flows TB

TECHNICAL NOTE 22_LINE2_TIA_Appendix C_D Future year AM Peak hour intersection flows TB

Technical Note 23_Park TIA_AppendixA_B_09_11_2012 TB

 

Park Street Concept Designs


TRT 2A Park Street Concept Design 1 of 12 November 2012

TRT 2A Park Street Concept Design 2 of 12 November 2012

TRT 2A Park Street Concept Design 3 of 12 November 2012

TRT 2A Park Street Concept Design 4 of 12 November 2012

TRT 2A Park Street Concept Design 5 of 12 November 2012

TRT 2A Park Street Concept Design 6 of 12 November 2012

TRT 2A Park Street Concept Design 7 of 12 November 2012

TRT 2A Park Street Concept Design 8 of 12 November 2012

TRT 2A Park Street Concept Design 9 of 12 November 2012

TRT 2A Park Street Concept Design 10 of 12 November 2012

TRT 2A Park Street Concept Design 11 of 12 November 2012

TRT 2A Park Street Concept Design 12 of 12 November 2012

TRT 2A Park Street Concept Design 12a of 12 November 2012

 

Minutes

2012-06-07 Arcadia Station

2012-06-21 Stakeholder meeting

2012-07-02 Universal Access Interest FGM

2012-07-04 Growthpoint Properties FGM

2012-07-05 Canadian High Commission FGM

2012-07-05 Ward 92 FGM

2012-07-09 Blue Bulls FGM

2012-07-09 Heritage FGM

2012-07-09 University of Pretoria FGM

2012-07-12 Gautrain FGM

2012-07-19 Feedback Meeting

2012-08-28 Ward 58 FGM

2012-08-29 Ward 80 FGM

2012-09-20 CLF Meeting

2012-10-09 Midcity FGM

2012-11-22 CLF Meeting

2013-03-07 CLF Meeting

 

Tshwane Rapid Transit (TRT) Line 2B Public Participation

TRT Line 2B


BID Line 2B FINAL

CoT_Line 2B Public Participation Infra Presentation- 09 Oct 2012_Hillcrest FGM

BRT Line 2 Land Use Transportation Assessment

 

TRT 2B - 18 Oct 2012 - Minutes App B

CoT_Line 2B Public Participation Infra Presentation- 18 Oct 2012 Minutes Appendix C

Tshwane Line 2B Traffic Simulation Results Minutes Appendix D

60237553_P_BRT2B_P001-018 290113 jan shoba-60237553_005

 

60237553_P_BRT2B_P001-018 290113-60237553_KEY PLAN

60237553_P_BRT2B_P001-018 290113-60237553_001

60237553_P_BRT2B_P001-018 290113-60237553_002

60237553_P_BRT2B_P001-018 290113-60237553_003

60237553_P_BRT2B_P001-018 290113-60237553_004

60237553_P_BRT2B_P001-018 290113-60237553_005

60237553_P_BRT2B_P001-018 290113-60237553_006

60237553_P_BRT2B_P001-018 290113-60237553_007

60237553_P_BRT2B_P001-018 290113-60237553_008

60237553_P_BRT2B_P001-018 290113-60237553_009

60237553_P_BRT2B_P001-018 290113-60237553_010

60237553_P_BRT2B_P001-018 290113-60237553_011

60237553_P_BRT2B_P001-018 290113-60237553_012

60237553_P_BRT2B_P001-018 290113-60237553_013

60237553_P_BRT2B_P001-018 290113-60237553_014

60237553_P_BRT2B_P001-018 290113-60237553_015

60237553_P_BRT2B_P001-018 290113-60237553_016

60237553_P_BRT2B_P001-018 290113-60237553_017

60237553_P_BRT2B_P001-018 290113-60237553_018

Minutes

2012-09-11 Ward 42, 46, 80 WHA, BRA FGM

2012-09-12 University of Pretoria FGM

2012-09-13 Ward 44, 45 and 47 FGM

2012-09-17 LRA FGM

2012-09-28 Universal Access Interest FGM

2012-10-09 Hillcrest Boulevard FGM

2012-10-18 Stakeholder Meeting

2012-10-26 Menlyn Shopping Centre FGM

2012-11-21 Lynnwood Road Business Owners FGM

2012-11-29 Menlynmaine FGM

2012-12-10 The Glen High School FGM

2013-01-25 Die Hoërskool Menlo Park FGM

2012-02-01 Laërskool Pretoria Oos FGM

2013-02-28 Stakeholder Meeting.

Komati S24G application for rectification


Appendix A - Requirements letter - 2012-03-16

Appendix C1 - SAS Komati Wetland Assessment 080812-Final v.2.0

Appendix C2 - E02 JNB 001300 - Komati S24G v.4.0

Appendix D - Draft EMP v.1.2 Dec 2012

BID_Komati_S24G_v.3 reduced size

Komati S24G_Draft EIR_v.1.2

Middelburg Herald advert

The Star advert

Komati S24G_Final EIR_v1.3.pdf

 

“Development of residential, commercial, retail and community facilities at Naledi Station, Soweto”

  • Draft Basic Assessment Report
•Last Updated on ••Monday•, 06 •May• 2013 02:52••